PJM to study SoftBank's 10-GW Ohio AI data center project under state agreement
SoftBank's Flagship project in Ohio, which includes new 765-kV transmission lines, 10 GW of data center load, and 10.2 GW of gas-fired generation, will undergo a grid impact study by PJM under a state-level agreement framework.
X Bluesky Threads LinkedIn Email
Coverage
Related stories
More coverage from around the web
Appeared in: 2026-10-14 (#2) · 2026-10-15 (#2)